What test results should you receive after a heat-pump installation?

Ask for a commissioning record that identifies your installed equipment, the checks performed, the results and any unresolved follow-up. “System runs” is not enough to explain whether the installer checked the conditions relevant to the equipment and installation.

PNNL's heat-pump guidance includes refrigerant-system checks and controls verification. For ducted systems, it also identifies airflow, total external static pressure, duct leakage and system performance checks. The applicable methods and acceptance criteria need to match the equipment and project. PNNL installation and commissioning guidance

Request a record you can connect to the job

Illustrative homeowner handover worksheet:

Record What to ask the installer to show What a vague entry leaves unanswered
Equipment identity Installed indoor and outdoor models and serial numbers Whether the record describes your system
Refrigerant work Applicable test method, result and acceptance basis What “charge checked” means
Controls Modes and settings verified for the installed arrangement Whether backup heat or other intended functions were checked
Ducted airflow Measured result and comparison with the design/equipment requirement Whether the existing ducts deliver the required airflow
Remaining work Specific issue, owner and return plan Whether “complete” includes unfinished checks

This is a request for professional documentation, not instructions for homeowners to perform refrigerant or electrical work.

Ask what a passing result means

A measurement without its units, method or acceptance criterion is difficult to interpret. Ask the installer to explain how the result compares with the relevant manufacturer or design requirement. Avoid borrowing a universal threshold from an unrelated system.

For a ducted installation, ask how airflow and static-pressure findings relate to the existing ductwork. Do not assume new equipment resolves an existing distribution problem. If a duct repair is proposed, ask which observation supports it and how completion will be verified.

An example with results and an unresolved item

Entirely fictional ducted-system record, November 16, 2026. Model identifiers and design references below are invented. These values are not recommended thresholds for any equipment.

Check Recorded result Acceptance reference for this example Recorded status
Equipment identity Outdoor HP-A / indoor AH-A; serials matched to invoice Accepted equipment schedule revision 2 Matched
Airflow 1,040 cfm at recorded heating fan setting Fictional project schedule: 1,000–1,100 cfm for this operating condition Within example’s range
Total external static pressure 0.72 in. w.c.; filter and fan setting recorded Fictional equipment limit: 0.60 in. w.c. in the same configuration Outside example’s limit; duct/filter investigation remains open
Controls Heating command and backup-heat sequence observed Fictional approved controls schedule C-2 Those functions checked; other modes separately recorded
Cooling performance No accepted result recorded Manufacturer method and permitted test conditions to be identified by installer Deferred; installer owes method, reason and return appointment

The airflow entry does not erase the static-pressure exception. The homeowner requests the actual measurement record, equipment criteria and a retest after corrections. A record that says only “passed” would conceal both unresolved items. Only a qualified installer should perform these measurements; the values above demonstrate how to read documentation.

Keep deferred tests explicit

Hypothetical example: The installer completes the agreed checks except for one performance verification that it says cannot be completed under the day's conditions. The record identifies the test, the reason for deferral, what can be established now and the follow-up arrangement.

The homeowner asks for that exception in writing rather than accepting either “everything passed” or an unexplained blank. Whether deferral is acceptable must be resolved for the particular equipment, contract and applicable requirements; this example does not approve a specific deferral.

Connect commissioning to the original proposal

Compare the installed equipment and operating arrangement with the accepted quote. If the model, controls or duct work changed, ask for the updated documentation and an explanation of how the change affects the design.

Keep the commissioning record with installation, warranty and permit documents. They answer different questions: a permit record is not the same artifact as measured commissioning results, and a warranty document does not show that a test passed.

Before installation, put the expected handover records in the agreed scope. After installation, reconcile the delivered records and unresolved items with that promise.

Evidence reviewed November 16, 2026. PNNL supplies the categories of checks; the homeowner worksheet is editorial synthesis. No installed system was inspected or tested.